مشاريع الطاقة الناجحة

Project Scope

Engineering & design,procurement, supply & delivery of all required materials & equipment to the work site, construction installation, testing & commissioning & put into service for installation of underground cable 33KV to feed the metro substation for L1,L3 & L5 from station 9052 to 9054 in Riyadh city.

Project NameInstallation of UGC 33 KV to feed Riyadh Metro stations
Project Valuation125 Million
Progress100%
Project Duration5 Years
Cable LengthPower Cable + 150KM - FOC Cable +67KM

Project Scope

Install, remove, replace, modify and maintain MV & LV overhead & underground distribution networks up to 36 KV

Project NameUnified Contract Distribution Network
Project Valuation128 Million
Progress60%
Project Duration5 Years

Project Scope

Design, engineering, supply, installation, operation & testing of 132 kV high voltage cables with all civil works, joint & termination works of cable, HDD works, fiber optic network laying works between & inside substations, protection works, cybersecurity solutions, & works of supplying, installing & configuring telecom devices inside the stations &2 Bay GIS Works.

Project NameConnection of Al-Nazim Central Station 132 KV in Riyadh City
Project Valuation215 Million
Progress20%
Project Duration22 Month
Cable LengthPower Cable +154KM - FOC Cable +57KM

Project Scope

Design, engineering, supply, installation, operation and testing of 132 kV high voltage cables with all civil works, joint & termination works of cable, HDD works, fiber optic network laying works between and inside substations, protection works, cybersecurity solutions, and works of supplying, installing and configuring telecom devices inside the stations.

Project NameConnection of Al-Aridh central station 132 in Riyadh City
Project Valuation42 Million
Progress20%
Project Duration22 Month
Cable LengthPower Cable +21KM - FOC Cable +8.5KM

Project Scope

Medium & low voltage electrical works, installation & supply of electrical switches & electrical transformers, supply & installation works for external lighting, communications works, water & drainage network works, water & floods, civil works, & works for supplying and installation of external fences.

Project NameWater Theme Park-AlQddiya Project
Project Valuation60 Million
Progress85%
Project Duration18 Month
Cable LengthPower Cable +21KM - FOC Cable +8.5KM

Project Scope

Design, engineering, supply, installation, operation and testing of 110 kV high voltage cables with all civil works, joint & termination works of cable, earth works, HDD works, and fiber optic network laying works between and inside substations.

Project NameConnection of Haram 3 substation in Madinah
Project Valuation76 Million
Progress25%
Project Duration21 Month
Cable LengthPower Cable +57KM - FOC Cable +21KM

Project Scope

Design, engineering, supply, installation, operation and testing of 110 kV high voltage cables with all civil works, joint & termination works of cable, earth works, HDD works, and fiber optic network laying works between and inside substations.

Project NameConnection of substation (Taiba West) In Madinah Network
Project Valuation68 Million
Progress25%
Project Duration21 Month
Cable LengthPower Cable +55KM - FOC Cable +19KM

Project Scope

Design, Engineer, Supply and Deliver all equipment & materials to the work site construct, Dismantle install, Test, Commission, & put the project into service

Project NameReplacement of Existing 33 KV UG Cable by new cable Phase
Project Valuation40 Million
Progress95%
Project Duration24 Month
Cable LengthPower Cable +75KM - FOC Cable +37KM

Project Scope

Design, engineering, supply, installation, operation and testing of 115 kV high voltage cables with all civil works, joint & termination works of cable, HDD works, fiber optic network laying works between and inside substations, protection works, cybersecurity solutions, and works of supplying, installing and configuring telecom devices inside the stations.

Project NameAn interconnection project between West Al Khobar Station & West Al Khobar Station-2
Project Valuation23 Million
Progress15%
Project Duration21 Month
Cable LengthPower Cable +5KM - FOC Cable +3KM

Project Scope

Design, engineering, supply, installation, operation & testing of 132 kV high voltage cables with all civil works, joint & termination works of cable, HDD works, fiber optic network laying works between & inside substations, protection works, cybersecurity solutions, & works of supplying, installing & configuring telecom devices inside the stations &1Bay GIS Works.

Project NameNew 132 KV U/G S/C Cable between 8781-8787 S/S In Wadi Ad-Dwaser (AL-Sulayal)
Project Valuation79 Million
Progress5%
Project Duration25 Month
Cable LengthPower Cable +19.5KM - FOC Cable +7KM

POWER SUCCESSFUL PROJECTS

مشروع تركيب كابلات أرضية 33 ك.ف. لتغذية محطات مترو الرياض

قيمة المشروع: 125 مليون ريال
مدة المشروع: 5 سنوات

العقد الموحد لشبكات التوزيع منذ عام 2008م

قيمة المشروع: 128 مليون ريال
مدة المشروع: 5 سنوات

ربط محطة النظيم المركزية جهد 132 ك.ف. في مدينة الرياض

قيمة المشروع: 215 مليون ريال
مدة المشروع: 22 شهر

ربط محطة العارض المركزية جهد 132 ك.ف. بمدينة الرياض

قيمة المشروع: 128 مليون ريال
مدة المشروع: 22 شهر

مشروع الحديقة المائية - القدية

قيمة المشروع: 42 مليون ريال
مدة المشروع: 18 شهر

تركيب شبكة كابلات أرضية جهد 100 ك.ف. لمحطة الحرم 3 الفرعية بالمدينة المنورة ضمن برنامج تقوية الشبكة للمدن الكبرى

قيمة المشروع: 76 مليون ريال
مدة المشروع: 21 شهر

تركيب شبكة كابلات أرضية جهد 100 ك.ف. لمحطة غرب طيبة الفرعية بالمدينة المنورة ضمن برنامج تقوية الشبكة للمدن الكبرى

قيمة المشروع: 68 مليون ريال
مدة المشروع: 21 شهر

مشروع استبدال الشبكة الكهربائية القديمة جهد 33 ك.ف. بمدينة الرياض

قيمة المشروع: 40 مليون ريال
مدة المشروع: 24 شهر

مشروع الربط تبادلي بين محطة غرب الخبر ومحطة غرب الخبر-2

قيمة المشروع: 23 مليون ريال
مدة المشروع: 21 شهر

مشروع ربط المحطة 8781 والمحطة 8787 بكابلات الجهد العالي 132 ك . ف . بوادي الدواسر

قيمة المشروع: 79 مليون ريال
مدة المشروع: 25 شهر

Progress 100%

Replace the feeder line cable A for Riyadh TV complex

Progress 20%

Replacement of 132KV LPOF U/G cable circuit 8092-8123, in Riyadh area

Progress 100%

Securing Electricity power to GSM's towers

Progress 21%

Replacement of 132KV LPOF U/G cable circuit 9014- 8058(B), in Riyadh area

Progress 85%

Replacement of Existing old 33KV UG cable circuits by new cables Il-phase in Riyadh

Progress 100%

Connection AL Malqaa's Substation with 132 KV network, Riyadh Area.

Progress 35%

Mechanical, Electrical & Plumbing MEP Works- ROSHAN

Progress 90%

Heat Water Treatment station in Al Kaharj area.

Progress 100%

Diriyah Gate Development Authority-MV works & water works

Progress 20%

Rerouting of 132 KV U/G cable Circuits between several power stations in central operation area of Riyadh city

Progress 45%

Rerouting of 132 KV U/G cable Circuits between several power stations in central operation area of Riyadh city

Progress 100%

Rerouting of 132 KV U/G cable Circuits between several power stations in central operation area of Riyadh city

Progress 100%

Infrastructure works Medium voltage network

Progress 100%

Install of Joints & Termination -Medium Voltage CAP2 Project

Progress 100%

Power MV Works-Ministry of National Guard

Progress 100%

Remal Schema Projects-MV Power